PHASE 2 PROJECT PHOTOS – CONSTRUCTION PHOTOS

Welding cilps along the column at the 2nd floor North Elevation.jpg Continued constructing metal racks for the electrical equipment at the 4th floor.jpg Continued installing ductwork at the 2nd floor Facing East.jpg Installed steal beams at the 4th floor East Elevation.jpg Started excavating Boiler Room for the underground electrical roughing Facing South-East.jpg Started installing ductwork at the 3rd floor Facing West.jpg Welded metal clips along column H-1 Facing East.jpg
Previous pageNext page Started excavating Boiler Room for the underground electrical roughing Facing South-East
Started excavating Boiler Room for the underground electrical roughing Facing South-East